Weather slows work on overpass project

By TESA CULLI

tesa.culli@register-news.com

MT. VERNON — The new overpass/interchange is still slated to be opened in September, however wet weather conditions have prevented some work from being undertaken on the Veterans Memorial Drive portion of the project.

“The Veterans Memorial Drive work has been affected by rain,” Greg Smothers of the Illinois Department of Transportation said. “We thought we would be able to gear that up again this week, but then the rain on the weekend put a lot of water on the ground and set it back again.”

But work has been continuing, with crews working at night, Smothers said.

“Crews have been painting the steel on the bridge and re-striping the pavement,” Smothers commented. “For the last couple of weeks, we’ve had a subcontractor erecting the highway lighting, and the signs, both directional and for food and gas vendors.”

In March, Smothers said if weather conditions cooperated, the project could be ready for opening in July, however, Smothers said although the July date has been moved back due to the rain, September is still ahead of the scheduled completion date.

When the construction bid for the project was awarded to E.T. Simonds Construction, the contract specified construction would begin by April 1, 2008, and the completion date is set by June 2010. E.T. Simonds was able to begin clearing brush and trees as well as some preliminary dirt work in March 2008, a month before the company was required to begin construction.

“We want to have it completed this work season,” Smothers said. “Right now, we’re estimating mid- to late September, if the weather holds out.”

Smothers said the overpass/interchange could be opened by September, but not all work completed, stating only “punch out items” would be left that could be completed while traffic was on the roadway.

“Even after it’s opened, there will still be some miscellaneous things that will need to be wrapped up,” Smothers said.

print this story  



autoconx
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Premier Guide
Hot Jobs

Water Treatment Plant Asst. Superintendent
Water Treatment Plant
Asst. Superintendent
Rend Lake Conservancy District, located at scenic Rend Lake in So
...>MORE

Enthusiastic, Dependable Individual for Office
Enthusiastic, dependable individual, for local office must be knowledgeable in MS Excel office & internet, non smoking o...>MORE

Fast Lube Technician
NOW HIRING Full and part time fast lube technicians. Experience not necessary but must have mechanical ability and be ab...>MORE

LPN or RN
Hiring Full-Time: LPN or RN at Pediatric office in Mt. Vernon. Must have valid nursing license in Illinois Benefits incl...>MORE

Paralegal
Paralegal needed for busy law office. Experience preferred but will train the right person. Need good organizational ski...>MORE

See all ads


 

Community Newspaper Holdings, Inc.CNHI Classified Advertising NetworkCNHI News Service
Associated Press content © 2009. All rights reserved. AP content may not be published, broadcast, rewritten or redistributed.
Our site is powered by Zope and our Internet Yellow Pages site is powered by PremierGuide.
Some parts of our site may require you to download the Flash Player Plugin.
View our Privacy Policy
Advertiser index